Critical path method CPM
Example:
I will be giving you a rea v glthe life example. I was working for my client in US. There I had to do funds work.
I was involved in fund merger and acquisition data grid validation. There I had to find any outliers in the fund grid. This was based on SQL queries. Also I had to prepare reports after each step.
The steps:
1) import the raw grid received from business
2) after successful import run pre investment scenario to get a report of contracts invested in the retiring funds
3) schedule merger reallocation transaction on each contract having investments in the retiring funds
4) run batch to execute the transaction
5) run post investment scenario to validate that all the contracts are now invested in the new fund.
Hence, 1 2 3 4 to 5 is the critical path, i.e the longest path
But, the task could also be completed with what is called the driving path i.e, 1 3 and 4 lies in the driving path.